- 1614 dwellings were consented in April 2022.
- In the year ending April 2022, 21,468 dwellings were consented in the region.
- 26 per cent of new dwellings consented in April 2022 were houses, 10 per cent were apartments and 64 per cent were townhouses, flats, units, retirement village units, or other types of attached dwellings.
- 32 dwellings were consented on Kāinga Ora or Tāmaki Regeneration Company owned land in April 2022.
- 1480 of dwellings consented in April 2022 were inside the RUB. Over the past 12 months, 93 per cent of new dwellings consented were inside the RUB.
- 19 per cent of dwellings consented were inside the 1500m walking catchments of the rapid transit network in April 2022.
- 919 dwellings were 'completed' by having a Code Compliance Certificate (CCC) issued in April 2022.
- In the year ending April 2022, 13,059 dwellings had a CCC issued.
- 631 new residential parcels under 5000m2 were created in May 2022.
- In the past 12 months, 10,073 new residential parcels under 5000m2 were created an average of 839 each month.
- In May 2022, 627 new residential parcels of all sizes were created inside the RUB.
- Long-term arrivals in March 2022 were 2879.
- 672 public housing applications have been housed in the December quarter 2021.